As of May 31th, 2008 for the work in the Aromatics Complex. The actual cumulative overall progress is 82.79% versus plan of 80.45% as indicated below, ahead by 2.34%. This month’s progress is ahead by 0.27%.

Phase
Weighted
(%)
This Month Progress Cumulative
Plan
Actual
Plan
Actual
0.11 0.11 100.00 100.00
1.94 2.09 94.01 94.58
5.61 6.24 52.59 59.63
0.00 0.00 0.00 0.00
2.76 3.03 80.45 82.79
Engineering
Procurement
Constrcution
Commissioning/Perfor.Test
Total

Health, Safety and Environmental Status

Up to Last Month This Month Total
12,193,357 1,562,447 13,755,804